Skebgy ASP Tank
Scheme details
Client
Draper Civil Engineering Ltd (for Galiford Try & Severn Trent Water)
JOS Value
£408k
Time
2024 - 16 weeks
Sectors
Water - Envirnonment
Purpose
To build an activated sludge process (ASP) for severn trent water, which is a compact solution to treat domestic wastewater.
Key Data
4 chamber ASP tank on Severn Trent treatment works
6m high steel formwork to provide the highest quality finish
160t reinforcement fixed
670m3 Concrete poured
JOS Supply
Labour
Temporary materials
Small plant (including concrete pumps)
JOS delivered the reinforced concrete works at Skegby Sewage Treatment Works (STW). This followed the success of a similar scheme at Kirkby-in-Ashfield which was delivered in a similar manner in collaboration with Draper Civil Engineering for Galliford Try and Severn Trent Water. Draper provided the groundworks, cranage and materials for JOS to execute the reinforced concrete works.
The development of the steel shuttering system in a pre-determined sequence designed with EFCO helped achieve the high-quality finish and maximise re-use of the system whilst bettering the programme.
This was carried out in an operational STW, working with the hazards of dirty water and the ongoing operational requirements of Severn Trent which were not impacted.