Perry Barr Flood Defence Scheme
Perry Barr flood Defence
Scheme details
Client
Jackson Civil Engineering
JOS Value
£1.2M
Time
2019 – 36 weeks
Sectors
Water - Environment
Purpose
Part of the Perry Barr & Witton Flood Risk Management Scheme. This structure controls the flow of water into the River Tame and helps prevent flooding in the Brookvale Road, Witton and Gravelly Park Industrial Area
Key Data
FRC Inlet structure for 4No. 15m Long Culverts
8m high headwalls with splayed fins reducing to 3m
Construction of 5No. baffle blocks & inset riprap for vehicle access
2,100m3 concrete poured
296t steel fixed
JOS Supply
Labour temporary materials & small plant.
JOS worked with Jackson Civil Engineering to deliver this scheme as part of the Perry Barr & Witton Flood Risk Management Scheme. We constructed the FRC works for the new structure whilst working adjacent to a temporariy diverted River Tame
We delivered the works safely and on time to the delight of our Client which built on our excellent relationship with Jackson Civil Engineering
A significant improvement we made to the outline methodology was to cast the headwalls in full height sections. This removed the need for a secondary upper level pour which would have required additional work at height and a longer programme. We also worked on the inlet & outlet structure similtaneously rather than linearly to better the programme.
Our team of specialist joiners worked closely with our formwork supplier at Huennebeck to guarentee the quality product for the splayed headwall was delivered to the plan.