Project Key Facts 
9,000m3 concrete placed 
1350t steel fixed 
Project Overview 
Sector 
Industrial 
 
Customer 
Principle Contractor: Buckingham Group for Britvic 
 
Location 
Rugby 
 
Total Cost 
£975,000 
 
Completed 
February 2018 
 
Duration 
9 Months 
Project Key Facts 
9,000m3 concrete placed 
1,350t steel fixed 
Project Description 
The works were to provide the sub-structure for a new bottling plant enabling an extension to the existing Britvic facility at Glebe Farm Industrial Estate. The heavy loading applied to the slab meant a heavily reinforced base slab with multi level accesses and retaining structures to facilitate this. This was ultimately enclosed in a 35m high warehouse. 
 
The JOS scope of work included the FRC elements of thefollowing; 
 
FRC Conveyor Tunnel & HGV Access Ramp,  
FRC Contiguous Wall capping beam,  
2000m2 FRC Low bay slab on bearing piles,  
7,500m2 550mm thick FRC High Bay Slab,  
12,000m2 yard slabs. 
 
JOS Structures worked with the Buckingham team to ensure the accellerated programme was achieved to deliver the operational facility on time. A major part of this was ensuring the prefabricated rolled out reinforcement for the heavily reinforced floor slab was installed quickly saving time over traditional steel fixing methods. 
"A well-resourced project with a great quality finish" - Mark Allwork - Buckingham Group Project Director 
 
 
Share this post: