ALCOA CNC MACHINE

Project Overview
Sector |
||
Customer |
Firtree |
|
Location |
Arconic, Kitts Green, Birmingham |
|
Total Cost |
£75,000 |
|
Completed |
November 2017 |
|
Duration |
12 Weeks |
Project Key Facts
To ensure all RC concrete was to Minimum levels.
Project Description
CNC Bed Plate foundation - JOS constructed a 1500mm deep RC foundation, which involved forming channels and pockets with polish finish fine tolerances.
Adjacent to the foundation was a RC 3.8m deep pit with perimeter upstands to form Bund.
JOS completed the works 1 week ahead of the 12 week schedule considering the program was reduced to 10 weeks due to the clients high demands.