Project Key Facts 
45m span skewed steel composite structure over the A50 
Abutments, Wing Walls, Deck and approach structures. 
Restricted working adjacent to live traffic within TM at weekends & nights and off peak day time. 
Project Overview 
Project Profile 
A50 Growth Corridor Project 
 
Customer 
Carillion PLC 
 
Location 
Uttoxeter 
 
Total Cost 
£750,000 
 
Completed 
November 2017 
 
Duration 
14 Months 
Project Description 
The scheme was to provide an improved junction between the A522 & the A50, which included JOS constructing a new bridge over the A50 in Uttoxeter. 
 
The scope of works was to carry out construction of two reinforced concrete abutments situated North and South of the A50 with retaining walls on either side enabling the prefabricated steel bridge to be positioned in placed. 
 
The Following works were to construct the RC Deck including Parapet, Apron slab and Wing Walls. 
 
The JOS team worked around the difficult TM constraints to successfully deliver the scheme safely and to a high standard the delight of the end customer (Staffordshire County Council).  
We are very pleased with the work that has been done and the way it has been undertaken, in a most professional and skilled manner, and to a high standard. 
 
- Staffordshire County Council 
 
 
Share this post:
Our site uses cookies. For more information, see our cookie policy. Accept cookies and close
Reject cookies Manage settings